ITP 76 Deployment operations
The deployment operations for ITP 76 were conducted out of the Russian Barneo ice camp (located at 89° 9’N, 11° 53’E on the morning of April 11) and completed rather quickly. The Russian MI-8 helicopter was brought to the Barneo runway after breakfast loaded with all of the buoys and deployment apparatus and departed with 8 deployment personnel at 9:50 UTC. One and a half hours and 273 km further upstream from Barneo a large ice floe greater than 250 m in diameter and surrounded by 1-2 m ridges was selected for the deployment site. No rafting was detected during test drilling which indicated ice thicknesses between 1.6 m and 2.0 m with 0.1 m freeboard and 0.2 m of snow on the surface.
Unloading of the helicopter, deployment of all 4 buoys (in air temperatures hovering around 30°C), and reloading of the deployment apparatus was completed in 6 hours while the helicopter remained on site. By 19:50 UTC all personnel and apparatus had returned safely at the Barneo ice camp.